[50772] in Hotline Meeting
Bldg. E19 - 2nd floor - 5/5 Electrical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 3 09:29:54 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104CC9@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'safety@mit.edu'" <safety@MIT.EDU>,
"'opsnote@mit.edu'"
<opsnote@MIT.EDU>,
"'joanf@mit.edu'" <joanf@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'benefits@mit.edu'"
<benefits@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 3 May 2000 08:23:28 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: safety@mit.edu; opsnote@mit.edu; joanf@mit.edu; shutdowns@mit.edu;
> benefits@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E19 - 2nd floor - 5/5 Electrical Shutdown Request
>
>
The following revised Electrical shutdown request for Bldg. E19 - 2nd floor
is again for your review and comment. Would you please let me know whether
this does or does not meet with your approval.
Thanks again.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E19 - 2nd floor
> Date: 5/5/00
> Day: Friday
> Time: 7:30 AM - 8:30 AM
> System: Electrical
> Duration: 1 hour
> Reason:
> Tie in new electrical panel.
>
> Effect:
> Loss of building power on second floor. This means that anything connected
> to an outlet will not operate (computers, telephones, copy machines, fax
> equipment) and some hall lighting. The fire alarm system will be
> operational. You might want to shutdown your computers Thursday evening
> before you leave.
>
>