[50771] in Hotline Meeting
Bldg. 4 - 061 and 069 - 5/9 Electrical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 3 08:18:02 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104CC8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'wyckoff@mit.edu'" <wyckoff@MIT.EDU>,
"'akelsey@mit.edu'"
<akelsey@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 3 May 2000 08:16:25 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: wyckoff@mit.edu; akelsey@mit.edu; mbj@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 4 - 061 and 069 - 5/9 Electrical Shutdown Request
>
>
The following electrical shutdown request for Bldg. 4 - 016 and 069 only on
Tuesday, 5/9 is for your review and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 4-061 and 069 only
> Date: 5/9/00
> Day: Tuesday
> Time: 7:30 AM - 11:30 AM
> System: Electrical
> Duration: 4 hours
> Reason:
> To connect feeder to different source by running into Rm. 069 and tieing
> into panel P-3.
>
> Effect:
> Loss of electrical services (computers, telephones, anything that has to
> be plugged into an outlet) in rooms 061 and 069 only during the 4-hour
> shutdown period.
>
>