[48791] in Hotline Meeting
Bldg. 8 - 413, 113, 213, 215, 313, 415, 419 & all bathrooms - 10/
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 14 10:49:34 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD139@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'carolr@mit.edu'" <carolr@MIT.EDU>, "'ccarey@mit.edu'"
<ccarey@MIT.EDU>,
"'kmartel@mit.edu'" <kmartel@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'trapaga@mit.edu'"
<trapaga@MIT.EDU>, "'krf@mit.edu'" <krf@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 14 Oct 1999 10:43:02 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: carolr@mit.edu; ccarey@mit.edu; kmartel@mit.edu; schedule@mit.edu;
> trapaga@mit.edu; krf@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 8 - 413, 113, 213, 215, 313, 415, 419 & all bathrooms
> - 10/19 - Shutdown Request
>
>
The following shutdown request for Bldg. 8 - 413, 113, 213, 215, 313, 415,
419 & all bathrooms on Tuesday, 10/19 is for your information and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 8 - 413, 113, 213, 215, 313, 415, 419 & all bathrooms
> Date: 10/19/99
> Day: Tuesday
> Time: 7 AM - 3 PM
> System: Cold Domestic Water
> Duration: 8 hours
> Reason:
> To replace old existing supply valve.
>
> Effect:
> Loss of cold domestic water in Building 8. This means that no toilets,
> bathroom, kitchen faucets or drinking fountains will be operational during
> the 8-hour shutdown period.
>
>