Bldg. 1-267, 167, 265, 267, 367 & 3rd floor - 10/18 - Shutdown Re
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 14 10:20:31 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD138@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dfucillo@mit.edu'" <dfucillo@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'magowen@mit.edu'" <magowen@MIT.EDU>,
"'mamullow@mit.edu'" <mamullow@MIT.EDU>,
"'mgibson@mit.edu'"
<mgibson@MIT.EDU>,
"'patdixon@mit.edu'" <patdixon@MIT.EDU>,
"'pmccosco@mit.edu'" <pmccosco@MIT.EDU>,
"'rlbras@mit.edu'"
<rlbras@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'scottc@mit.edu'" <scottc@MIT.EDU>,
"'skanode@mit.edu'"
<skanode@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 14 Oct 1999 10:14:05 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: dfucillo@mit.edu; shutdowns@mit.edu; magowen@mit.edu;
> mamullow@mit.edu; mgibson@mit.edu; patdixon@mit.edu; pmccosco@mit.edu;
> rlbras@mit.edu; schedule@mit.edu; scottc@mit.edu; skanode@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 1-267, 167, 265, 267, 367 & 3rd floor - 10/18 -
> Shutdown Request
>
>
The following shutdown request for Bldg. 1-267, 167, 265, 267, 367 & 3rd
floor on Monday, 10/18 is for your information and comment. Would you
please let me know whether this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 1-267, 167, 265, 267, 367 & 3rd floor
> Date: 10/18/99
> Day: Monday
> Time: 7 AM - 3 PM
> System: Cold Domestic Water
> Duration: 8 hours
> Reason:
> To remove and replace existing old supply shutoff valve with new ball
> valve.
>
> Effect:
> Loss of cold domestic water. This means that no toilets, bathroom,
> kitchen faucets or drinking fountains will be operational during the
> 8-hour shutdown period. The toilets in Building 2 and other area buildings
> will be operating however.
>
>