Bldg. 8 - 309 A, B, C, 111 - 10/12 - Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 6 13:13:30 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD0E2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ccarey@mit.edu'" <ccarey@MIT.EDU>, "'krf@mit.edu'" <krf@MIT.EDU>,
        "'molecan@mit.edu'" <molecan@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 6 Oct 1999 13:07:09 -0400 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	ccarey@mit.edu; krf@mit.edu; molecan@mit.edu; shutdowns@mit.edu;
> opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 8 - 309 A, B, C, 111 - 10/12 - Shutdown Request
> 
> 
The following elecrrical, 110V, light circuit shutdown for Bldg. 8 - 309 A,
B, C and 111 (light circuit only) on Tuesday, 10/12 is for your information
and comment.  Would you please let me know whether this does or does not
meet with your approval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 8 - 309 A, B, C and 111
> Date: 10/12/99
> Day: Tuesday
> Time: 6 AM - 8 AM
> System: Electrical, 110V and light circuit (111 only)
> Duration: 2 hours
> Reason: 
> To repipe existing circuits that were damaged during construction of
> bathrooms.
> 
> Effect: 
> Loss of building power, computers, telephones and lighting during 2-hour
> shutdown in the above listed rooms.
> 
> 