Steam pressure was lost at about 11am due to boiler trip at the Cogeneration
Plant. Other boilers were immediately brought on and are ramping up. Steam
pressure to east campus is nearly back to normal. Main and west campus are
at about 60%. All should be back to normal by about 12:45pm. We apologize
for any inconvenience caused.