Bldgs. 2 and 6 - 9/20 - Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 15 11:13:09 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90ACFEE@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ndpope@mit.edu'" <ndpope@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 15 Sep 1999 11:07:13 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	ndpope@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. 2 and 6 - 9/20 - Shutdown Request
> 
> 
The following shutdown request for Bldg. 2 and 6 on Monday, 9/20 is for your
information and comment.  Would you please let me know whether this does or
does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872



> Status: Normal
> Building:  2 and 6 
> Date: 9/20/99
> Day: Monday
> Time: 7:30 AM - 2:30 PM
> System: Chilled Water, Supply Cooling, Hood Make-up
> Duration: 7 hours
> Reason: 
> Tie in new 4" lines for laser lab project.
> 
> Effect: 
> Loss of chilled water supply and return in rooms listed below: Bldg. 6 -
> 019, 022, 021, 135, 133, 131, 129, 128, 132, 123, 235 Suite, 205 Suite,
> 233, 221 Suite, Air Handler 1 - floors 3 & 4 North; 120, 219, 218M, 215,
> 216, 214, 211, 212, 209, 210, 207, 207A, 208, 206, 205, 203, 204, Air
> Handler 2 (floors 3 and 4 South) 321, 326, 325, 327, 328, 329, 330, 331A,
> 332, 331, 333, 333A, 335, 334, 435, (434, 433, 433A, 431, 432) Occupied.
> (430, 429, 428, 427, 426, 425, 423, 22, 421, 420, 419, 418, 417)
> Unoccupied.
> 
> Bldg. 2-121, 321.
> Please note: 2-125, 225, and 325 are not affected.
> 
> 
> 