Bldg. 9 - Floors 2 thru 6 - 9/23 and 24 - Revised Critical Shutdo

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 15 10:04:35 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90ACFEC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'deedc@mit.edu'" <deedc@MIT.EDU>, "'gallant@mit.edu'"
	 <gallant@MIT.EDU>,
        "'mlavalle@mit.edu'" <mlavalle@MIT.EDU>,
        "'randy@mit.edu'" <randy@MIT.EDU>, "'src@mit.edu'" <src@MIT.EDU>,
        "'westlund@mit.edu'" <westlund@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 15 Sep 1999 09:58:19 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	deedc@mit.edu; gallant@mit.edu; mlavalle@mit.edu; randy@mit.edu;
> src@mit.edu; westlund@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 9 - Floors 2 thru 6 - 9/23 and 24 - Revised Critical
> Shutdown Request
> 
> 
The following revised Critical shutdown request for Bldg. 9 - floors 2 thru
6 only on Thursday, 9/23 and Friday, 9/24 is for your review.  Would you
please let me know whether this does or does not meet with your approval.

Thank you again.

Andrea Nichols
Operations Center
8-7872 

> Status: Critical
> Building: 9 - floors 2 thru 6 only
> Date: 9/23/24
> Day: Thursday
> Time: 9 AM - 5 PM each day
> System: Supply ventilation, cooling and heating
> Duration: 8 hours each day (16 in all)
> Reason: 
> Install 2 heating hot water coils and remove old ones.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating (off for
> summer) on floors 2 thru 6 only (Air Handler 1, Supply Fan 1). This will
> not affect the basement or first floor - those floors will be covered by
> Air Handler 2 which will remain operational.
> 
> 