[48464] in Hotline Meeting
Bldg. 9 - 9/23 and 24 - Critical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 14 15:12:33 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90ACFE8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'deedc@mit.edu'" <deedc@MIT.EDU>, "'gallant@mit.edu'"
<gallant@MIT.EDU>,
"'jobrien@mit.edu'" <jobrien@MIT.EDU>,
"'mlavalle@mitvma.mit.edu'" <mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'"
<ndk@MIT.EDU>, "'randy@mit.edu'" <randy@MIT.EDU>,
"'src@mit.edu'"
<src@MIT.EDU>,
"'westlund@mit.edu'" <westlund@MIT.EDU>,
"'alexnow@mit.edu'" <alexnow@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 14 Sep 1999 15:06:19 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> mlavalle@mitvma.mit.edu; ndk@mit.edu; randy@mit.edu; src@mit.edu;
> westlund@mit.edu; alexnow@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 9 - 9/23 and 24 - Critical Shutdown Request
>
>
The following Critical shutdown request for Bldg. 9 on 9/23 and 9/24 is for
your review and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 9
> Date: 9/23/24
> Day: Thursday
> Time: 9 AM - 5 PM each day
> System: Supply ventilation, supply cooling and supply heating
> Duration: 8 hours each day
> Reason:
> Install 2 heating hot water coils and remove old ones.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating (off for
> summer) during this 2-day shutdown. (Air Handler 1, Supply Fan 1).
>
>