[48099] in Hotline Meeting
Bldg. 2 - 8/10 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 5 12:23:26 1999
Message-Id: <9D3AC86A7244D311919900805FBE000006AD95@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'akelsey@mit.edu'"
<akelsey@MIT.EDU>,
"'duggins@math.mit.edu'" <duggins@math.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'mbj@mit.edu'" <mbj@MIT.EDU>,
"'nolan@math.mit.edu'" <nolan@math.mit.edu>,
"'preacher@mit.edu'"
<preacher@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'sdimond@mit.edu'" <sdimond@MIT.EDU>,
"'seyferth@wccf.mit.edu'"
<seyferth@wccf.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 5 Aug 1999 12:21:16 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: capozzi@math.mit.edu; akelsey@mit.edu; duggins@math.mit.edu;
> shutdowns@mit.edu; mbj@mit.edu; nolan@math.mit.edu; preacher@mit.edu;
> schedule@mit.edu; sdimond@mit.edu; seyferth@wccf.mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 2 - 8/10 - Shutdown Request
>
>
The following shutddown request for bldg. 2 on Wednesday, 8/10 is for your
review and comment. Would you please let me know whether this does or does
not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 2
> Date: 8/10/99
> Day: Wednesday
> Time: 8 AM - 12 Noon
> System: Hot Domestic Water
> Duration: 4 hours
> Reason:
> New air conditioning unit will not fit under domestic hot water pipes in
> room 048. System will have to be shutdown while unit is being installed.
>
> Effect:
> Loss of hot domestic water in Building 2. This means there will be no hot
> water in bathroom or kitchen faucets during the shutdown period.
>
>