Bldg. 26 - Entire Building - 7/20 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 13 14:29:40 1999

Message-Id: <ECFE33C8A3D4D111917900805FBE00008FCE47@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dudley@mit.edu'" <dudley@MIT.EDU>,
        "'gfp170@mitrlevm.mit.edu'"
	 <gfp170@mitrlevm.mit.edu>,
        "'kates@mit.edu'" <kates@MIT.EDU>,
        "'ljtrudel@mit.edu'" <ljtrudel@MIT.EDU>, "'lsc@mit.edu'" <lsc@MIT.EDU>,
        "'mparker@mit.edu'" <mparker@MIT.EDU>,
        "'radams@mit.edu'"
	 <radams@MIT.EDU>,
        "'rmbesset@mit.edu'" <rmbesset@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 13 Jul 1999 14:21:24 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	dudley@mit.edu; gfp170@mitrlevm.mit.edu; kates@mit.edu;
> ljtrudel@mit.edu; lsc@mit.edu; mparker@mit.edu; radams@mit.edu;
> rmbesset@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 26 - Entire Building - 7/20 Shutdown Request
> 
> 
The following shutdown request for Bldg. 26 - entire building on Tuesday,
July 20 is for your review and comment.  Would you please let me know
whether this does or does not meet with your approval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 26 - enire building
> Date: 7/20/99
> Day: Tuesday
> Time: 7:30 AM - 11:30 AM
> System: Chilled Water
> Duration: 4 hours
> Reason: 
>  New chilled water lines must be tied into system.
> 
> Effect: 
> Loss of chilled water (air conditioning)in building as well as loss of
> chilled water to Lazer Labs.
> 
> 