RE: Rescheduled - Bldg. N51 and N52 - 5/20 - Steam Shutdown Reque

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri May 14 11:25:19 1999

Message-Id: <ECFE33C8A3D4D111917900805FBE00007B8085@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mleen@mit.edu'" <mleen@MIT.EDU>,
        "'altonero@mit.edu'"
	 <altonero@MIT.EDU>,
        "'earls@mit.edu'" <earls@MIT.EDU>, "'menos@mit.edu'"
	 <menos@MIT.EDU>,
        "'rmurray@mit.edu'" <rmurray@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'cbdewart@mit.edu'" <cbdewart@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Fri, 14 May 1999 11:14:53 -0400
Mime-Version: 1.0
Content-Type: text/plain

Dear Everyone:
It has been requested that this shutdown be rescheduled to May 20. Would
you please let me know if this new date better fits your schedule.

Thank you.

Andrea Nichols

> ----------
> From: 	Andrea Nichols
> Sent: 	Friday, May 14, 1999 10:07 AM
> To: 	'mleen@mit.edu'; 'altonero@mit.edu'; 'earls@mit.edu';
> 'menos@mit.edu'; 'rmurray@mit.edu'; 'schedule@mit.edu';
> 'shutdowns@mit.edu'; 'cbdewart@mit.edu'
> Cc: 	Shutdown
> Subject: 	Bldg. N51 and N52 - 5/20 - Steam Shutdown Request
> Importance: 	High
> 
> > To: 	mleen@mit.edu; altonero@mit.edu; earls@mit.edu;
> menos@mit.edu;
> > rmurray@mit.edu; schedule@mit.edu; shutdowns@mit.edu;
> cbdewart@mit.edu
> > Cc: 	shutdown@plant.mit.edu
> > Subject: 	Bldg. N51 and N52 - 5/20 - Steam Shutdown Request
> > 
> > 
> The following shutdown request for Bldg. N52 (which will also affect
> Bldg. N51) on 5/20 is for your information and comment. Would you
> please
> let me know whether this does or does not meet with  your approval.
> 
> Thank you.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: N52 and N51
> > Date: 5/20/99
> > Day: Thursday
> > Time: 7:30 AM - 2:30 PM
> > System: Low Pressure Steam
> > Duration: 7 hours
> > Reason: 
> > Relocating existing steam lines.
> > 
> > Effect: 
> > Loss of  pressure steam only during shutdown period. This means that
> > there will be no heating hot water (or perimeter heat) in N51 and
> N52
> > during the shutdown period.
> > 
> > 
> 