Bldg. E19-722 - 5/25 - 28 - Asbestos Removal Notification

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 11 13:10:16 1999

Message-Id: <ECFE33C8A3D4D111917900805FBE00007B8049@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bshannon@mit.edu'" <bshannon@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>, E-Zone <E-Zone@MIT.EDU>,
        Tim Donaghey
	 <TDonaghe@PLANT.MIT.EDU>, "'tr6@mit.edu'" <tr6@MIT.EDU>,
        "'jdoucett@mit.edu'" <jdoucett@MIT.EDU>,
        "'tdoyle@mit.edu'"
	 <tdoyle@MIT.EDU>,
        Jack Narcotta <JNarcott@PLANT.MIT.EDU>,
        "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Tue, 11 May 1999 13:04:06 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	bshannon@mit.edu; shutdowns@mit.edu; E-Zone; Tim Donaghey;
> tr6@mit.edu; jdoucett@mit.edu; tdoyle@mit.edu; Jack Narcotta;
> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu; mmahoney@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: 	Bldg. E19-722 - 5/25 - 28 - Asbestos Removal
> Notification
> 
> 
The following asbestos removal notification for Bldg. E19 - 722 on 5/25
thru 5/28 is for your information.  If you have any questions about
this, please contact Mr. Jack Narcotta at 3-6352.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E19-722
> Date: 5/25/28
> Day: Tuesday
> Time: 7 AM (5/25) - 4 PM (5/28)
> System: None - asbestos removal notification only
> Duration: 4 days
> Reason: 
> Removal of 100 square feet of floor tile in Rm. 722.
> 
> Effect: 
> Asbestos removal area will be cordoned off in Rm. 722.
> 
> 