Bldg. E53 - All Floors - 5/14 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri May 7 11:54:48 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE00007B801D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lhill@mit.edu'" <lhill@MIT.EDU>,
"'michaela@mit.edu'"
<michaela@MIT.EDU>,
"'rdavies@mit.edu'" <rdavies@MIT.EDU>,
"'janets@mit.edu'" <janets@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 7 May 1999 11:48:38 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: lhill@mit.edu; michaela@mit.edu; rdavies@mit.edu;
> janets@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E53 - All Floors - 5/14 - Shutdown Request
>
>
The following shutdown request for Bldg. E53 - All floors on 5/14 is for
your review and comment. Would you please let me know whether this does
or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E53 - All Floors
> Date: 5/14/99
> Day: Friday
> Time: 7 AM - 3 PM
> System: Supply ventilation, cooling and heating
> Duration: 8 hours or until complete
> Reason:
> To repair leaking coils on air Handler 1 (PM# 700092).
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating during
> the shutdown period.
>
>