Bldgs. 33 Basement & 1st Floor and 35 - 4/5 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Apr 1 10:52:00 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'dickp@mit.edu'"
<dickp@MIT.EDU>,
"'rdavies@mit.edu'" <rdavies@MIT.EDU>,
"'gerwent@mit.edu'" <gerwent@MIT.EDU>,
"'stiffler@mit.edu'"
<stiffler@MIT.EDU>,
"'kate@lids.mit.edu'" <kate@lids.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 1 Apr 1999 10:47:08 -0500
> To: schedule@mit.edu; dickp@mit.edu; rdavies@mit.edu;
> gerwent@mit.edu; stiffler@mit.edu; kate@lids.mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 33 Basement & 1st Floor and 35 - 4/5 - Shutdown
> Request
>
>
The following shutdown request for Bldgs. 33 and 35 on 4/5 is for your
information and comment. Would you please let me know whether this does
or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 33 Basement & 1st Floor and 35
> Date: 4/5/99
> Day: Monday
> Time: 7 AM - 3 PM
> System: Chilled Water Pumps
> Duration: 8 hours
> Reason:
> Electrical demo in Bldg. 33 in the basement requires the pumps to be
> disconnected and reconnected to a new transfomer.
>
> Effect:
> Loss of chilled water (air conditioning) in Bldg. 33 and Bldg. 35
> during shutdown period.
>
>