[47080] in Hotline Meeting

home help back first fref pref prev next nref lref last post

FW: Approved - Bldg. W8 - 4/2 - All Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Apr 1 09:28:41 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
        Jim Hunt <jahunt@plant.mit.edu>,
        Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
        "'vcrayton@mit.edu'" <vcrayton@MIT.EDU>,
        Carl Hagge
	 <CHagge@PLANT.MIT.EDU>, Joe Kay <jakay@PLANT.MIT.EDU>,
        "'stucrew@mit.edu'" <stucrew@MIT.EDU>
Cc: RM-3rdShift <rm-3rdshift@MIT.EDU>,
        "'rm-shutdown@mit.edu'"
	 <rm-shutdown@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Thu, 1 Apr 1999 09:23:49 -0500

The following approved shutdown for Bldg. W8 on 4/2 AM - All Power - is
for your information.

Andrea Nichols
> >Operations Center
> >8-7872
> >
> >> Status: Normal
> >> Building: W8
> >> Date: 4/2/99
> >> Day: Friday
> >> Time: 2 AM - 6 AM
> >> System: All Power
> >> Duration: 4 hours
> >> Reason:
> >> Replace Electric panel.
> >>
> >> Effect:
> >> Loss of Power: Bldg. power, computers, lighting, corridors/stair
> >> lighting, boiler (heat); Water: heating hot water.
> 
> 
> 
> 

home help back first fref pref prev next nref lref last post