Bldgs. E17 and E18 480 Volt Electrical Shutdown Request for 12/18

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Dec 9 11:19:46 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'wardd@mit.edu'" <wardd@MIT.EDU>, "'jmganno@mit.edu'"
	 <jmganno@MIT.EDU>,
        "'shyoung@mit.edu'" <shyoung@MIT.EDU>,
        "'aufiero@mit.edu'" <aufiero@MIT.EDU>,
        "'rmelo@mit.edu'" <rmelo@MIT.EDU>,
        "'jmedeiro@mit.edu'" <jmedeiro@MIT.EDU>, Plant-All <Plant-ALL@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'cjbeal@mit.edu'" <cjbeal@MIT.EDU>, "'amba@mit.edu'" <amba@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 9 Dec 1998 11:10:58 -0500

> To: 	wardd@mit.edu; jmganno@mit.edu; shyoung@mit.edu;
> aufiero@mit.edu; rmelo@mit.edu; jmedeiro@mit.edu; Plant-All;
> opsnote@mit.edu; shutdowns@mit.edu; cjbeal@mit.edu; amba@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. E17 and E18 480 Volt Electrical Shutdown Request
> for 12/18
> 
> 
The following shutdown request for Bldgs. E17 and E18 on 12/18 is for
your information and comment. Would you please let me know whether or
not this meets with your approval.

There will be one more shutdown to follow; probably in 2 - 4 weeks. As
soon as I have this information I will send it along to your.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E17 and E18
> Date: 12/18/98
> Day: Friday
> Time: 5:30 AM - 6:30 AM
> System: 480 Volt Electrical (Same effect as shutdown on 11/20/98)
> Duration: 1 hour
> Reason: 
> Replace main breaker - rewire electrical supply to Motor Control
> Center.
> 
> Effect: 
> Power: Loss of Freight Elevator in E17 and E18; Water:  loss of
> chilled water (air conditioning) in E17 and E18 Animal Quarters as
> well as remainder of E17 and E18, E17-347B, 350, 350A and 360;  loss
> of heating hot water in E17 and !8; air: supply ventilation, supply
> cooling, supply heating, exhaust-laboratory, exhaust-general,
> exhaust-toilet, compressed control, compressed lab and lab vacuum air.
> Note:  There will be an emergency generator operating to handle the
> critical equipment in the Animal Quarters in E17 and E18.  It is
> imperative that this work be complete by 6:30 AM as cash washers will
> be reporting to work at that time.
> 
> 