RE: To be Rescheduled -Bldg. 56 & 16- Continuation of Fire Alarm
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Dec 2 08:11:04 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mare@mit.edu'" <mare@MIT.EDU>, "'mparker@mit.edu'" <mparker@MIT.EDU>,
"'mbj@mit.edu'" <mbj@MIT.EDU>, "'sorrento@mit.edu'" <sorrento@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'loudib@mit.edu'"
<loudib@MIT.EDU>,
"'claudia@mit.edu'" <claudia@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'pguyer@mit.edu'" <pguyer@MIT.EDU>, "'rha@mit.edu'" <rha@MIT.EDU>,
"'bmalone@mit.edu'" <bmalone@MIT.EDU>,
"'carolr@mit.edu'" <carolr@MIT.EDU>, "'edc@mit.edu'" <edc@MIT.EDU>,
"'kej@mit.edu'" <kej@MIT.EDU>, "'childs@mit.edu'" <childs@MIT.EDU>,
"'wogan@mit.edu'" <wogan@MIT.EDU>,
"'bdfollst@mit.edu'"
<bdfollst@MIT.EDU>,
"'puffer@mit.edu'" <puffer@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Wed, 2 Dec 1998 08:09:27 -0500
Dear Everyone:
The shutdown time has been changed from 7 AM to 8 AM. Therefore this
work will occur on Sunday, 12/6 from 8 AM - 4 PM. If this is a problem,
please let me know.
Thank you.
Andrea Nichols
> Operations Center
> 8-7872
>
> Status: Normal
> > Building: 56 & 16
> > Date: 12/6/98
> > Day: Sunday
> > Time: 8 AM - 4 PM
> > System: Fire Alarm Audible testing
> > Duration: 8 hours
> > Reason:
> > Testing on Saturday, 11/21 was not complete. Simplex and
> Cambridge
> * > Fire Department would like to continue this work until
> it is complete
>
> > Effect: Loss of fire alarm system and smoke detectors.
> Audible testing would take place. Again this would be short bursts of
> sound and announcements would be made prior to each testing.
>
>
>