[45908] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldgs. W31 and W32 Electric Power and Lighting Shutdown Request f

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 20 12:07:42 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'djmartin@mit.edu'" <djmartin@MIT.EDU>,
        "'kenstone@mit.edu'"
	 <kenstone@MIT.EDU>,
        "'regillya@mit.edu'" <regillya@MIT.EDU>,
        "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 20 Nov 1998 12:06:23 -0500

> To: 	djmartin@mit.edu; kenstone@mit.edu; regillya@mit.edu;
> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu; mwf@mit.edu;
> shutdowns@mit.edu; opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. W31 and W32 Electric Power and Lighting Shutdown
> Request for 12/1
> 
> 
The following Electric Power and Lighting shutdown request for Bldgs.
W31 and W32 on 12/1 is for your review and comment.  Would you please
let me know whether or not this meets with your approval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: W31 and W32
> Date: 12/1/98
> Day: Tuesday
> Time: 5:30 AM - 7:00 AM
> System: All Electric Power and Lighting
> Duration: 1 1/2 hours
> Reason: 
> To install new main breaker and perform metering upgrades.
> 
> Effect: 
> Loss of Power:  access controls, building power, elevators, computers,
> telephones and lighting;  Water:  hot domestic water pumps (water for
> kitchen and bathroom faucets), heating hot water pumps (heating for
> bldg.); Air:  supply ventilation, supply cooling, supply heating,
> exhaust-laboratory, exhaust-general, exhaust toilet and compressed
> control air. 
> 
> 