[45353] in Hotline Meeting
FW: Approved - Bldgs. 4 and 12 Chilled Water Shutdown Request for
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 13 14:42:53 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
"'graposa@mit.edu'" <graposa@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
RM-Support
<RM-Support@MIT.EDU>, Warren Scott <WScott@PLANT.MIT.EDU>
Date: Tue, 13 Oct 1998 14:19:09 -0400
The following approved shutdown for Bldgs. 4 and 12 (Chilled Water) on
10/14
is for your information.
Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 4 and 12
> > Date: 10/14/98
> > Day: Wednesday
> > Time: 7:00 AM - 3:00 PM
> > System: Chilled Water
> > Duration: 8 hours
> > Reason:
> > To tie in new 4" chilled water line to feed a new Air Handler unit
> in
> > building 4.
> >
> > Effect:
> > Loss of chilled water (air conditioning) in both buildings 4 and 12
> > during shutdown period.
>
>
>