[45352] in Hotline Meeting
RE: Bldgs. 4 and 12 Chilled Water Shutdown Request for 10/14
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 13 14:34:05 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jcentor@mit.edu'" <jcentor@MIT.EDU>,
"'cwilkes@mit.edu'"
<cwilkes@MIT.EDU>,
"'rroscoe@mit.edu'" <rroscoe@MIT.EDU>, "'frc@mit.edu'" <frc@MIT.EDU>,
"'vesau@mit.edu'" <vesau@MIT.EDU>, "'menos@mit.edu'" <menos@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'zqueen@mit.edu'" <zqueen@MIT.EDU>,
"'sandylo@mit.edu'" <sandylo@MIT.EDU>,
"'pennysun@mit.edu'"
<pennysun@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Tue, 13 Oct 1998 14:10:54 -0400
Dear Everyone:
Update ... Some of you have questioned why we are asking for this
shutdown again since the work was to have been done on October 6th. I
just found out that this was not the case because the valves were not
holding and therefore the work was not done.
PPL would like to do this again tomorrow because they have come up with
a new way of dealing with the valves so that they will hold and the
pipes.
I hope this explanation helps out a bit. Please let me know if this work
would be all right or not.
Thank you again.
Andrea Nichols
> ----------
> From: Andrea Nichols
> Sent: Tuesday, October 13, 1998 11:31 AM
> To: graham@mit.edu; juliec@mit.edu; mbj@mit.edu; ccarey@mit.edu;
> krj@mit.edu; jcentor@mit.edu; cwilkes@mit.edu; rroscoe@mit.edu;
> frc@mit.edu; jsheahan@mit.edu; vesau@mit.edu; 'menos@mit.edu';
> 'shutdowns@mit.edu'; 'genh@mit.edu'; 'zqueen@mit.edu';
> 'bkaynor@mit.edu'; 'sandylo@mit.edu'; rrhonda@mit.edu; lpaul@mit.edu;
> sandylo@mit.edu; pennysun@mit.edu; Andrea Nichols
> Cc: Shutdown
> Subject: RE: Bldgs. 4 and 12 Chilled Water Shutdown Request for
> 10/14
> Importance: High
>
> Dear Everyone:
> Would you be good enough to respond to this shutdown request by 12:30
> PM today. If I don't hear from you I will assume (something I never
> like to do) that this will be all right with you.
>
> Thank you and I look forward to hearing from you.
> Andrea Nichols
>
> ----------
> > Subject: Bldgs. 4 and 12 Chilled Water Shutdown Request
> for 10/14
> >
> >
> The following chilled water (air conditioning) request for
> Bldgs. 4 and
> 12 on 10/14 is for your information and comment. Would you
> please let me
> know whether or not this meets with your approval.
>
> Thanks very much.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 4 and 12
> > Date: 10/14/98
> > Day: Wednesday
> > Time: 7:00 AM - 3:00 PM
> > System: Chilled Water
> > Duration: 8 hours
> > Reason:
> > To tie in new 4" chilled water line to feed a new Air Handler
> unit in
> > building 4.
> >
> > Effect:
> > Loss of chilled water (air conditioning) in both buildings 4
> and 12
> > during shutdown period.
>
>
>