[45102] in Hotline Meeting
Bldg. N42 - 2nd floor Emergency Shutdown for 9/25 - TBD
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 25 15:13:09 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-2ndShift <rm-2ndshift@MIT.EDU>, RM-3rdShift <rm-3rdshift@MIT.EDU>,
"'jdb@mit.edu'" <jdb@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
Dan Crovo <DCrovo@PLANT.MIT.EDU>, Warren Scott <WScott@PLANT.MIT.EDU>,
Carl Hagge <CHagge@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
RM-Support
<RM-Support@MIT.EDU>
Date: Fri, 25 Sep 1998 15:05:48 -0400
> To: RM-2ndShift; RM-3rdShift; jdb@mit.edu; shutdowns@mit.edu;
> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu;
> mmahoney@mit.edu; D-Zone; Dan Crovo; Warren Scott; Carl Hagge
> Cc: shutdown@plant.mit.edu; RM-Support
> Subject: Bldg. N42 - 2nd floor Emergency Shutdown for 9/25 - TBD
>
>
The following Emergency shutdown for Bldg. N42 - 2nd floor on 9/25 is
for you information. If you have any questions about this, please
contact Mr. Dan Crovo at 3-4756.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: N42 - 2nd floor
> Date: 9/25/98
> Day: Friday
> Time: 3:00 PM - TBD
> System: Supply cooling
> Duration: 4 hours or more
> Reason:
> Compressor failure on Roof Top Fan #2
>
> Effect:
> Loss of mechanical cooling on 2nd floor - supply ventilation will be
> operational however.
>
>