[45102] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. N42 - 2nd floor Emergency Shutdown for 9/25 - TBD

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 25 15:13:09 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-2ndShift <rm-2ndshift@MIT.EDU>, RM-3rdShift <rm-3rdshift@MIT.EDU>,
        "'jdb@mit.edu'" <jdb@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
        Dan Crovo <DCrovo@PLANT.MIT.EDU>, Warren Scott <WScott@PLANT.MIT.EDU>,
        Carl Hagge <CHagge@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        RM-Support
	 <RM-Support@MIT.EDU>
Date: Fri, 25 Sep 1998 15:05:48 -0400

> To: 	RM-2ndShift; RM-3rdShift; jdb@mit.edu; shutdowns@mit.edu;
> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu;
> mmahoney@mit.edu; D-Zone; Dan Crovo; Warren Scott; Carl Hagge
> Cc: 	shutdown@plant.mit.edu; RM-Support
> Subject: 	Bldg. N42 - 2nd floor Emergency Shutdown for 9/25 - TBD
> 
> 
The following Emergency shutdown for Bldg. N42  - 2nd floor on 9/25 is
for you information.  If you have any questions about this, please
contact Mr. Dan Crovo at 3-4756.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Emergency
> Building: N42 - 2nd floor
> Date: 9/25/98
> Day: Friday
> Time: 3:00 PM - TBD
> System: Supply cooling
> Duration: 4 hours or more
> Reason: 
> Compressor failure on Roof Top Fan #2
> 
> Effect: 
> Loss of mechanical cooling on 2nd floor - supply ventilation will be
> operational however.
> 
> 

home help back first fref pref prev next nref lref last post