FW: Approved - Bldg. NW14 (Bathrooms Only) Shutdown Request for 8

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 26 10:19:39 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
        "'cust-coach@mit.edu'"
	 <cust-coach@MIT.EDU>,
        "'anton@mit.edu'" <anton@MIT.EDU>,
        Kevin Connolly
	 <kmconnol@PLANT.MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
        Dan Crovo
	 <DCrovo@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        RM-Support
	 <RM-Support@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'aldona@mit.edu'" <aldona@MIT.EDU>
Date: Wed, 26 Aug 1998 10:11:26 -0400

The following approved shutdown for Bldg. NW14 (Bathrooms Only) on 8/29
is for your information.

Andrea Nichols
Operations Center
8-7872

> > Status: Normal
> > Building: NW14
> > Date: 8/29/98
> > Day: Saturday
> > Time: 6:00 AM - 3:30 PM
> > System: hot and cold domestic water
> > Duration: 9 1/2 hours
> > Reason: 
> > Relocate piping on 2nd floor (it was requested that this work be
> done
> > on Saturday).
> > 
> > Effect: 
> > Loss of hot and cold domestic water --no bathrooms will be
> operational
> > during shutdown period.
> 
> 