[44652] in Hotline Meeting
RE: Revised W20-204 thru 206 and 316 thru 326 Shutdown Request no
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 26 09:51:04 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwf@mit.edu'" <mwf@MIT.EDU>, "'pdc@mit.edu'" <pdc@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Wed, 26 Aug 1998 09:44:38 -0400
The following revised shutdown request for Bldg. W20-240 thru 206 and
316 thru 326 now on 8/27 PM - 8/28 AM is for your information. Would you
please let me know if the revised dates and times are acceptable to you
or not.
Thank you again.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: W20-204 thru 206 & 316 thru 326
> > Date: 8/27 PM - 8/28 AM
> > Day: Thursday PM - Friday AM
> > Time: 11:00 PM (8/27) - 3:00 AM (8/28)
> > System: Chilled Water secondary loop
> > Duration: 4 hours
> > Reason:
> > Repair leak on pipe in main computer cell.
> >
> > Effect:
> > Loss of chilled water (air conditioning) in the above listed rooms
> > (Networks, Toscanini's, Lobdell Dining Hall and 3rd Floor Southeast.
This will not affect Athena as the floors can be valved off
separately.
>
>
>