[44633] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE: Canceled for now --Approved - Bldg. 39 - 301W & Clean Rooms l

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Aug 25 10:15:10 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, B-Zone <B-Zone@MIT.EDU>,
        Warren Scott <WScott@PLANT.MIT.EDU>,
        "Michael St. Croix"
	 <mstcroix@PLANT.MIT.EDU>,
        Cust-Coach <cust-coach@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, RM-Support <RM-Support@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Tue, 25 Aug 1998 10:08:43 -0400

The above filter change/shutdown for Bldg. 39 301W & clean rooms on 8/29
has been canceled for now. As soon as I have a new date for this project
I will let you know.

Andrea Nichols

> ----------
> From: 	Andrea Nichols
> Sent: 	Tuesday, August 18, 1998 9:58 AM
> To: 	'dcarlson@mit.edu'; 'cappucci@mit.edu'; 'jfreeman@mit.edu';
> 'mmahoney@mit.edu'; B-Zone; Warren Scott; Michael St. Croix;
> Cust-Coach
> Cc: 	Shutdown; RM-Support; 'shutdowns@mit.edu'
> Subject: 	FW: Approved - Bldg. 39 - 301W & Clean Rooms located in
> 6th Floor Mech. Rm. - AH2 Filter Change/Shutdown Request for 8/29
> Importance: 	High
> 
> The following approved shutdown/filter changes for Bldg. 39 (Air
> Handler
> 2) on 8/29 is for your information.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > > Status: Normal
> > > Building: 39 -301W and Clean Rooms
> > > Date: 8/29/98
> > > Day: Saturday
> > > Time: 7:00 AM - 1:00 PM
> > > System: Supply ventilation, cooling and heating
> > > Duration: 6 hours
> > > Reason: 
> > > Filter change on Air Handler 2 
> > > 
> > > Effect: 
> > > Loss of supply ventilation, cooling and heating
> > 
> > 
> 