[43615] in Hotline Meeting
FW: Approved - Bldg. N10 Hot and Cold Water Shutdown Request for
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 28 15:04:20 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>, D-Zone
<D-Zone@MIT.EDU>,
David Sodano <dsodano@PLANT.MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
RM-Support <RM-Support@MIT.EDU>
Date: Thu, 28 May 1998 15:00:37 -0400
The following approved shutdown for Bldg. N10 Hot and Cold Water on 6/2
is for your information.
Andea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: N-10
> > Date: 6/2/98
> > Day: Tuesday
> > Time: 9:00 AM - 5:00 PM
> > System: Hot and cold domestic water
> > Duration: 8 hours
> > Reason:
> > Install backflow on water main.
> >
> > Effect:
> > Loss of hot and cold domestic water. This means that all restrooms,
> > bathroom facilities and drinking fountains will not be operating
> > during the shutdown period.
> >
> >
>