[42512] in Hotline Meeting
Bldg. 26 shutdown request for 3/26
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Mar 20 09:19:31 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'radams@mitlns.mit.edu'"
<radams@mitlns.mit.edu>,
"'rmbesset@mit.edu'" <rmbesset@MIT.EDU>,
"'gfp170@mitrlevm.mit.edu'" <gfp170@mitrlevm.mit.edu>,
"'mparker@mit.edu'" <mparker@MIT.EDU>,
"'ljtrudel@mit.edu'"
<ljtrudel@MIT.EDU>,
"'shippie@mit.edu'" <shippie@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 20 Mar 1998 09:18:06 -0500
> To: schedule@mit.edu; radams@mitlns.mit.edu; rmbesset@mit.edu;
> gfp170@mitrlevm.mit.edu; mparker@mit.edu; ljtrudel@mit.edu;
> shippie@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 26 shutdown request for 3/26
>
>
The following shutdown request for Bldg. 26 on 3/26 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 26
> Date: 3/26/98
> Day: Thursday
> Time: 9:00 AM - 1:00 PM
> System: Medium and low pressure steam
> Duration: 4 hours
> Reason:
> Replace relief valve
>
> Effect:
> Loss of heating hot water (heat), hot domestic water (bathroom and
> kitchen faucets) and medium and low pressure steam.
>
>