RE: Bldg. 6 - 132, 134, 136, Panel DP-1 Electrical Shutdown on 3/

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 10 12:12:11 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'lnolan@math.mit.edu'" <lnolan@math.mit.edu>,
        "'elp@mit.edu'" <elp@MIT.EDU>, "'guidess@mit.edu'" <guidess@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
        Neil Tomlinson
	 <NTomlins@PLANT.MIT.EDU>,
        James Sullivan <jsulliva@PLANT.MIT.EDU>,
        Manuel Moreira <mmoreira@PLANT.MIT.EDU>
Date: Tue, 10 Mar 1998 12:11:05 -0500

Dear everyone:
  I am resending this shutdown request because I have found out that it
is the same request that was issued on 1/14/98 (which as canceled
because of experiments.) 

Would you please let me know if this has your approval or disapproval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> ----------
> From: 	Andrea Nichols
> Sent: 	Monday, March 9, 1998 3:25 PM
> To: 	'juliec@mit.edu'; 'mbj@mit.edu'
> Cc: 	Shutdown
> Subject: 	Bldg. 6 - 132 Electrical Shutdown on 3/19 PM - 3/20 AM
> Importance: 	High
> 
> The following requested shutdown for Bldg. 6 - 132, 134, 136 and Panel
> DP-1 on 3/19 PM - 3/20 AM
> is for your review and comment. Would you please let me know if this
> has
> your approval or not.
> 
> Thanks very much Julie.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 6 - 132, 134, 136 & Panel DP-1
> > Date: 3/19/20
> > Day: Thursday
> > Time: 11:00 PM - 7:00 AM
> > System: Electrical - 208V, 110V. Electrical power outlets and fan
> coil units located in 124, 126A, 123, 125, 128A, 128, 127, 130, 127,
> 132, 131, 134, 133 and 138
> > Duration: 8 hours
> > Reason: 
> > To tie in new 250 A circuit breaker to 208V buss duct riser by
> outside contractor.
> > 
> > Effect: 
> > Loss of Bldg. power (supply ventilation), computers, lighting during
> > shutdown period.
> > 
> > 
> 