Bldg. 12 Water Shutdown Request for 3/17

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 10 11:25:57 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'naylor@mit.edu'" <naylor@MIT.EDU>, "'genh@mit.edu'" <genh@MIT.EDU>,
        "'jcentor@mit.edu'" <jcentor@MIT.EDU>,
        "'jasmith@mit.edu'" <jasmith@MIT.EDU>,
        "'jbartel@mit.edu'"
	 <jbartel@MIT.EDU>,
        "'bkaynor@mit.edu'" <bkaynor@MIT.EDU>,
        "'zqueen@mit.edu'" <zqueen@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 10 Mar 1998 11:24:41 -0500

> To: 	schedule@mit.edu; shutdowns@mit.edu; naylor@mit.edu;
> genh@mit.edu; jcentor@mit.edu; jasmith@mit.edu; jbartel@mit.edu;
> bkaynor@mit.edu; zqueen@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 12 Water Shutdown Request for 3/17
> 
> 
The following shutdown request for Bldg. 12 (all water) on 3/17 is for
your review and comment. Would you please let me know if this has your
approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 12
> Date: 3/17/98
> Day: Tuesday
> Time: 5:00 PM - 10:00 PM
> System: Cold and hot domestic water
> Duration: 5 hours
> Reason: 
> Install backflow preventer in main water lines.
> 
> Effect: 
> Loss of all cold and hot domestic water. This means that there will be
> no restroom, kitchen facilities or drinking fountains operating during
> this shutdown period..
> 
> 