FW: Approved -- Bldg. NE43 - 9th Floor Perimeter Spaces Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 26 14:33:24 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Gerry Hughes <ghughes@PLANT.MIT.EDU>, B-Zone <B-Zone@MIT.EDU>,
        dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU, ksutherl@MIT.EDU,
        sdverify@MIT.EDU
Cc: shutdowns@plant.mit.edu, shutdown@MIT.EDU, opsnote@MIT.EDU,
        cust-coach@MIT.EDU
Date: Wed, 26 Nov 1997 14:31:00 -0500

The following approved shutdown for Bldg. NE43 - 9th floor perimeter
spaces on 12/1 is for your information.

Andrea Nichols
Operations Center
8-7872

> > Status: Normal
> > Building: NE43 - 9th floor perimeter spaces
> > Date: 12/1 - 3 or 5/97
> > Day: Monday, Wednesday or Friday
> > Time: 7:00 AM (12/1 - 2/15 (est)
> > System: Induction heating/cooling
> > Duration: initially 3-5 days then 2 1/2 months (or more or less)
> > Reason: 
> > Repairs and modifications to heating/cooling system to allow proper
> > individual temperature control
> > 
> > Effect: 
> > Loss of chilled water (a/c) and heating hot water - supply cooling,
> > supply heating and compressed control air. 
> > 
> > After 3 - 5 days heating and cooling should be provided via Air
> > Handler Units on the 10th floor. The system should be back to normal
> > sometime after the new year (estimate 2/15/97).  There is enough
> > heating on the 9th floor that should carry over.
> > 
> > 
> 