NW14 - Entire Building Shutdown Request for 9/19

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 12 14:32:01 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: fulton@psfc.mit.edu, hrycaj@psfc.mit.edu, aldona@MIT.EDU,
        D-Zone
	 <D-Zone@MIT.EDU>
Cc: shutdown@plant.mit.edu, shutdowns@MIT.EDU
Date: Fri, 12 Sep 1997 14:30:43 -0400

> To: 	fulton@psfc.mit.edu; hrycaj@psfc.mit.edu; aldona@mit.edu; D-Zone
> Cc: 	shutdown@plant.mit.edu; shutdowns@mit.edu
> Subject: 	NW14 - Entire Building Shutdown Request for  9/19
> 
> 
The following shutdown request for Bldg. NW14 on 9/19 is for your
information and comment. Would you please let me know if this has your
approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: NW14 - Entire Building
> Date: 9/19/97
> Day: Friday
> Time: 7:00 AM - 3:00 PM
> System: Chilled Water
> Duration: 8 hours
> Reason: 
> Replacing inlet check valve for chilled water pump
> 
> Effect: 
> Loss of chilled water and supply cooling (air conditioning)
> 
> 