[38146] in Hotline Meeting
Requested Critical Shutdown - Bldg. NW21 - 5/4
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri May 2 09:38:19 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'fulton@psfc.mit.edu'"
<fulton@psfc.mit.edu>,
"'hrycag@psfc.mit.edu'"
<hrycag@psfc.mit.edu>
Cc: D-Zone <D-Zone@MIT.EDU>
Date: Fri, 2 May 1997 09:39:12 -0400
The following requested Critical shutdown for Bldg. NW 21 on 5/4 is for
your information and comment. Would you please let me know if this has
your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
Critical
Building: NW21
System: Air Handler 2, Supply Fan 1 (supply ventilation
and cooling)
Date: 5/4
Day: Sunday
Time: 6:00 AM - 6:00 PM
Duration: 12 hours
Reason: To repair chilled water coils
Effect: Loss of supply ventilation and cooling.