Requested Shutdowns - Bldg. 6 - 5/8 and 5/9

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Apr 30 13:49:20 1997

Date: Wed, 30 Apr 1997 13:48 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, adams@mitlns.mit.edu, juliec@MIT.EDU,
        mbj@MIT.EDU, acherron@MIT.EDU, edc@MIT.EDU, elp@MIT.EDU,
        farideh@MIT.EDU
X-Envelope-To: acherron@mit.edu, edc@mit.edu, elp@mit.edu, farideh@mit.edu,
 juliec@mit.edu, mbj@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, schedule@mit.edu, adams@mitlns.mit.edu, juliec@mit.edu,
   mbj@mit.edu, acherron@mit.edu, edc@mit.edu, elp@mit.edu, farideh@mit.edu"

The following shutdown requests are for your information and comment.
Would you please let me know if these have your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Building:       6 - 029 and 114 (would affect Chemistry and Physics
                only)
System:         Fan exhaust hood - PM#703372 and 714467
Date:           4/8
Day:            Thursday
Time:           8:00 AM - 10:30 AM
Duration:       2 1/2 hours
Reason:         Annal preventive maintenance work
Effect:         Loss of exhaust laboratory air

Building:       6 - 3rd floor labs (would affect Chemistry only)
System:         Supply Fan (Air Handler 4 - PM#707207 and
                Air Handler 5 - PM#708080)
Date:           5/9
Day:            Friday
Time:           8:00 AM - 10:00 AM
Duration:       2 hours
Reason:         Annual preventive maintenance work
Effect:         Loss of supply ventilation, cooling and heating during
                shutdown period.

Building:       6 - all rooms with hoods (would affect EMS, Chemistry,
                Physics and Spectroscopy)
System:         Hood make-up air (PM#703370)
Date:           5/9
Day:            Friday
Time:           8:00 AM - 10:00 AM
Duration:       2 hours
Reason:         Annual preventive maintenance work
Effect:         Loss of supply ventilation during shutdown period

Building:       6 - 1st fhru 4th floors and room 321 (would affect
                Chemistry, EMS, Physics and Spectroscopy)
System:         Supply Fan Air Handler 2 - PM#703204 and
                Supply Fan Air Handler 3 - PM#703293 (supply
                ventilation)
Date:           5/9
Day:            Friday
Time:           12:30 PM - 2:30 PM
Duration:       2 hours
Reason:         Annual preventive maintenance work
Effect:         Loss of supply ventilation during shutdown period.

home help back first fref pref prev next nref lref last post