Requested Shutdown - Bldg. 37 - 3/17

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Mar 12 10:14:13 1997

Date: Wed, 12 Mar 1997 10:10 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, opsnote@MIT.EDU, pbauer@MIT.EDU,
        benford@space.mit.edu, cmo@space.mit.edu, breslau@space.mit.edu,
        rcf@space.mit.edu
X-Envelope-To: opsnote@mit.edu, pbauer@mit.edu, schedule@mit.edu,
 shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, schedule@mit.edu, opsnote@mit.edu, pbauer@mit.edu, benfo
   rd@space.mit.edu, cmo@space.mit.edu, breslau@space.mit.edu, rcf@space.mit.edu
   "

The following requested shutdown for Bldg. 37 for 3/17 is for your
information and comment. Would you please let me know if this has your
approval or not.

Thank you.

Andrea Nichols
Operations Center/PM Office
8-7872

Building:       37 - all floors except rooms facing Vassar St. (North
                Zone)
System:         Supply Fan 1
Date:           3/17
Day:            Monday
Time:           8:00 AM - 10:00 AM
Duration:       1.5 hours within above time frame
Reason:         48 filter changes
Effect:         Loss of supply ventilation, cooling and heating for 1.5
                hours.