[37350] in Hotline Meeting
Emergency Shutdown Request - Bldgs. 4 and 10 - 3/13
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Mar 12 09:20:13 1997
Date: Wed, 12 Mar 1997 09:19 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, mbj@MIT.EDU, acherron@MIT.EDU,
jcentor@MIT.EDU, rroscoe@MIT.EDU, cehart@MIT.EDU, sheahan@MIT.EDU,
ndk@MIT.EDU, vjames@mitvmc.mit.edu, rrhonda@MIT.EDU, heatherm@MIT.EDU,
elp@MIT.EDU
X-Envelope-To: acherron@mit.edu, cehart@mit.edu, elp@mit.edu, heatherm@mit.edu,
jcentor@mit.edu, mbj@mit.edu, ndk@mit.edu, rrhonda@mit.edu, rroscoe@mit.edu,
schedule@mit.edu, sheahan@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, schedule@mit.edu, mbj@mit.edu, acherron@mit.edu, jcentor
@mit.edu, rroscoe@mit.edu, cehart@mit.edu, sheahan@mit.edu, ndk@mit.edu, vjam
es@mitvmc.mit.edu, rrhonda@mit.edu, heatherm@mit.edu, elp@mit.edu"
The following Emergency shutdown for Bldgs. 4 and 10 for 3/13 is for
your information. If you have a concern, please feel free to contact
me.
Thank you.
Andrea Nichols
Operations Center
8-7872
Building: 4 and 10
System: All hot and cold water (bathrooms, labs, kitchen sinks,
drinking fountains, feed to de-ionized water in 4-429)
Date: 3/13
Day: Thursday
Time: 7:00 AM - 1:00 PM
Duration: 6 hours
Reason: Broken and leaking riser valve
Effect: Loss of hot and cold domestic water, hot and cold lab
process water which means no bathroom facilities,
drinking fountains, kitchen sinks, feed to de-ionized water in
4-429 and lab water available during shutdown period.