RE:bldg. 14s shutdown

daemon@ATHENA.MIT.EDU (jjmorey@MIT.EDU)
Tue Mar 11 13:16:43 1997

From: jjmorey@MIT.EDU
To: hotline@MIT.EDU
Date: Tue, 11 Mar 1997 13:16:41 EST


------- Forwarded Message

Received: from PACIFIC-CARRIER-ANNEX.MIT.EDU by po8.MIT.EDU (5.61/4.7) id AA21390; Tue, 11 Mar 97 12:32:19 EST
Received: from MITVMA.MIT.EDU by MIT.EDU with SMTP
	id AA23309; Tue, 11 Mar 97 12:32:15 EST
Received: from MITVMA.MIT.EDU by mitvma.mit.edu (IBM VM SMTP V2R3)
   with BSMTP id 2147; Tue, 11 Mar 97 12:32:27 EST
Received: from MITPPL.BITNET (NJE origin OPCTEMP2@MITPPL) by MITVMA.MIT.EDU
 (LMail V1.2b/1.8b) with BSMTP id 8540; Tue, 11 Mar 1997 12:32:27 -0500
Received: from MITPPL.BITNET by MITPPL.BITNET (PMDF #12255) id
 <01IGDK6BG5808WW4DG@MITPPL.BITNET>; Tue, 11 Mar 1997 12:32 EDT
Date: Tue, 11 Mar 1997 12:32 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
Subject: Your Request re AH2 in 14S on 3/12
To: jjmorey@MIT.EDU
Message-Id: <01IGDK6BG5808WW4DG@MITPPL.BITNET>
X-Envelope-To: jjmorey@mit.edu
X-Vms-To: IN%"jjmorey@mit.edu"

Hi JJ:

I spoke w/Mr. Macintyre who is the supervisor of the filter changing
crew. He said there would no problem in changing the filter on AH2
first tomorrow morning at 7:30 AM.

FYI.

andrea

The following filter change notificaiton/shutdown request for Bldg. 14S
for 3/12 is for your information and comment. Would you please let me
know if this has your approval or not.

Thank you.

Andrea Nichols
Operations Center/PM Office
8-7872

Building:       14S
System:         Air Handler 1 - services 1st thru 3rd East Wing
                Air Handler 2 - services basement stacks
                Air Handler 3 - services Main Library S.E. 1st & 2nd flrs.
                Supply Fan 4 - services Main Library S.W. 1st & 2nd flrs.
                Air Handler 5 - services Hayden Gallery - 1st flr.
Date:           3/12
Day:            Wednesday
Time:           7:30 AM - 2:30 PM
Duration:       6 hours/15 minutes within above time frame
Effect:         Minimal - loss of supply ventilation/cooling although each air
                handler and supply fan will be down one at a time for one-hour
                fifteen minutes at a time.
/* ---------- */

Hi Andrea -

the above shutdown should be fine however we would prefer the :
Air Handler 2 - services basement stacks

be done first thing.

Thanks

3/10
3pm
JJ
/* ---------- */

------- End of Forwarded Message