Rescheduled Requested Shutdown - Bldg. 2 - Now for 1/25
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Jan 14 09:25:05 1997
Date: Tue, 14 Jan 1997 09:22 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, c-zone@MIT.EDU, duggins@MIT.EDU,
capozzi@math.mit.edu, nolan@math.mit.edu, var@MIT.EDU, mbj@MIT.EDU,
daisymae@MIT.EDU
X-Envelope-To: c-zone@mit.edu, daisymae@mit.edu, duggins@mit.edu, mbj@mit.edu,
schedule@mit.edu, shutdowns@mit.edu, var@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, schedule@mit.edu, c-zone@mit.edu, duggins@mit.edu, capoz
zi@math.mit.edu, nolan@math.mit.edu, var@mit.edu, mbj@mit.edu, daisymae@mit.e
du"
The following rescheduled requested shutdown for Bldg. 2 formerly for 1/18
and now for 1/25 is for your information and comment. This is going to
be a huge operation, new pipes will be brought in, laid out, volumes of water
will be flushed through -- all designed to enhance the operation of the
system. Would you please let me know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
Building: 2
System: All chilled water cooling--both process and climate
control.
Date: 1/25/97 (formerly 1/18)
Day: Saturday
Time: 6:00 AM - 8:00 PM
Duration: 14 hours
Reason: Basement chilled water pumping station discharge piping
alterations within 2-006.
Effect: Loss of chilled water and cold lab process water via
chilled/Hx: ex. lasar cooling.