The following requested shutdown for Bldg. 18 - Basement Labs for
1/15/97 is for your information and comment. Would you please let me
know if this has your approval or disapproval.
Thank you.
Andrea Nichols
Operations Center
8-7872
Building: 18 - Basement Labs
System: Air Handler 1 - Supply Fan 3
Date: 1/15/97
Day: Wednesday
Time: 8:00 AM - 12 noon
Duration: 4 hours
Reason: Remove/disconnect duct work to fix reheat coil.
Effect: Loss of supply ventilation, cooling and heating during
shutdown perod.