[34941] in Hotline Meeting
Requested Shutdown - Bldg. 26 - 2nd, 3rd & 4th floors 9/26/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Sep 24 12:57:21 1996
Date: Tue, 24 Sep 1996 10:54 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, adams@mitlns.mit.edu,
gfp170@mitrlevm.mit.edu
X-Envelope-To: schedule@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, schedule@mit.edu, adams@mitlns.mit.edu, gfp170@mitrlevm.
mit.edu"
The following requested shutdown for Bldg. 26 - 2nd, 3rd & 4th floors
for 9/26 is for your information and review. Would you please let me
know if this shutdown is either acceptable to you or unacceptable.
Thanks very much.
Andrea Nichols
Operations Center
8-6651
Building: 26 - 2nd, 3rd & 4th floors
System: Chilled water (isolation valves each floor, 2nd floor
end of run)
Date: 9/26/96
Day: Thursday
Time: 7:00 AM - 3:00 PM
Duration: 8 hours
Reason: Tie in on corridor main
Effect: Loss of chilled water (no a/c) during shutdown period.