Requested Shutdown - Bldg. 68 - 9/16 - 20/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Sep 6 11:53:03 1996

Date: Fri, 6 Sep 1996 11:27 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, jfucillo@MIT.EDU, shyoung@MIT.EDU, jgannon@MIT.EDU
X-Envelope-To: jfucillo@mit.edu, jgannon@mit.edu, shutdowns@mit.edu,
 shyoung@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, jfucillo@mit.edu, shyoung@mit.edu, jgannon@mit.edu"

The following requested shutdown of Bldg. 68 from 9/10- 11; 9/12-13 and
9/16 - 20/96 is for your information and review. Would you please let me know
if this shutdown has your approval or disapproval.

Thanks very much.

Andrea Nichols
Operations Center
8-6651

Building:       68 - sub-basement - animal quarters
System:         Exhaust Fan 10: 9/10 - Smoke Detectors
                Exhaust Fan 9 : 9/11 - Smoke Detectors
Date:           9/10 and 9/11
Day:            Tuesday and Wednesday
Time:           7:00 AM - 3:00 PM each day
Duration:       8 hours each day
Reason:         Steel structural modifications to fans' support
                members: penthouse welding
Effect:         None - fans provide back-up to each other. No
                impact to operation, one fan will remain operational.

Building:       68 - sub-basement - animal quarters
System:         Exhaust Fan 8: September 12 - smoke detectors
                Exhaust Fan 7: September 13 - smoke detectors
Date:           9/12 & 13
Day:            Thursday and Friday
Time:           7:00 AM - 3:00 PM each day
Duration:       8 hours each day
Reason:         Steel structural modifications to fans' support members
                to fan: penthouse welding
Effect:         No impact to operation, one fan will remain
                operational; fans provide back-up to each other.

Building:       68 - Building Systems Group, Lab/General Exhaust
                Back-Up Fans
System:         Exhaust Fan 1: September 16 - smoke detectors
                Exhaust Fan 2: September 17 - smoke detectors
                Exhaust Fan 3: September 18 - smoke detectors
                Exhaust Fan 4: September 19 - smoke detectors
                Exhaust Fan 5: September 19 - smoke detectors
                Exhaust Fan 6: September 20 - smoke detectors
Date:           9/16 - 20
Day:            Monday through Friday
Time:           7:00 AM - 3:00 PM each day
Duration:       8 hours each day
Reason:         Steel structural modifications to fans' support members
                to fan: penthouse welding. One fan + 20% of next fan
                will be worked one each day.
Effect:         Exhaust Fans #1-6 will be down 6 hours each. Only one
                of these fans will be down at a time. The building will
                not see any disruption in service or climate as a result of
                this shutdown.