Requested Shutdown - Bldgf. 16 - 8/17/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Aug 13 12:14:02 1996

Date: Tue, 13 Aug 1996 12:09 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu"

The following information for the requested shutdown of Bldg. 16 is for
your review. Would you please let me know if this shutdown has your
approval or disapproval.

Thanks very much.

Andrea Nichols
Operations Center
8-6651

Building:       16 - Basement up to and including 4th floor
System:         Fan Coil Units on these floors only
Date:           8/17/96
Day:            Saturday
Time:           5:00 AM - 3:00 PM
Duration:       10 hours
Reason:         Have to tie-in new chilled water piping
Effect:         No air conditioning during shutdown.