Rescheduled Requested Shutdown - Bldg. 26 - Domestic Water System

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Jul 31 10:51:32 1996

Date: Wed, 31 Jul 1996 10:47 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, gfp170@mitrlevm.mit.edu,
        adams@mitlns.mit.edu
X-Envelope-To: schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, schedule@mit.edu, gfp170@mitrlevm.mit.edu, adams@mitlns.
   mit.edu"


The following rescheduled requested shutdown is for your review and information.
Would you please let me know if the rescheduled requested date have your
approval or disapproval.

Thanks very much for your assistance.

Andrea Nichols
Operations Center
8-6651


Building:       26
System:         Hot and cold domestic water supply
Date:           8/08/96
Day:            Thursday
Time:           8:00 AM - 2:00 PM
Duration:       6 hours
Reason:         Installation of two backflow preventers to protect City
                water.
Effect:         Loss of hot domestic, hot lab process, cold domestic,
                cold lab process water.