Requested Critical Shutdown -Monday, July 1- E23, E25, E32, E33, E34,

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Jun 28 14:26:46 1996

Date: Fri, 28 Jun 1996 14:23 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, mmahoney@MIT.EDU, rcoate@wccf.mit.edu,
        schedule@MIT.EDU, e-zone@MIT.EDU, relices@MIT.EDU, mmarshal@MIT.EDU,
        hmadnic@MIT.EDU
X-Envelope-To: e-zone@mit.edu, hmadnic@mit.edu, mmahoney@mit.edu,
 mmarshal@mit.edu, opsnote@mit.edu, relices@mit.edu, schedule@mit.edu,
 shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, opsnote@mit.edu, mmahoney@mit.edu, rcoate@wccf.mit.edu,
   schedule@mit.edu, e-zone@mit.edu, relices@mit.edu, mmarshal@mit.edu, hmadnic@
   mit.edu"

The following information pertains to the requested critical shutdown
for next Monday, July 1.  Would you please let me know if this is
acceptable or not.  I can be contacted via return e-mail or at 8-6651.

Thanks very much for your assistance.

Andrea Nichols
Operations Center
8-6651

Critical
Building:       E23, E25, E32, E33, E34, E38, E40, E42, E51, E52 and
                E56
System:         Campus "XA" fire alarm loop.
Date:           July 1, 1996
Day:            Monday
Time:           7:30 AM - 9:30 AM
Duration:       2 hours
Reason:         To relocate "XA" loop in E2 Senior House due to
                construction.
Effect:         Building fire alarm systems will still continue to
                operate, but not report back to the Operations Center.
                If a problem occurs, the individual office will have
                to call X3-1500 for assistance.