Shutdowns

daemon@ATHENA.MIT.EDU (JOHN NARCOTTA)
Thu Feb 29 14:06:21 1996

Date: Thu, 29 Feb 1996 14:05 EDT
From: JOHN NARCOTTA <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: shutdowns@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU, sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, sdverify@mit.edu,
 shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, dcarlson@mit.edu, cappucci@mit.edu, sdverify@mit.edu"

The following information pertains to upcoming shutdowns.

Building:       42 (FCS Computer Room)
System:         Supply ventilation, supply cooling and supply heating
Date:           3/25/96
Day:            Monday
Time:           8:00 AM - 9:00 AM
Duration:       1 hour
Reason:         Change final filters
Effect:         Loss of supply ventilation, supply cooling and supply
                heating for 1 hour.

Critical Shutdown
Building:       3 - 155
System:         Exhaust Hood (#703399--PM states it is a general
                exhaust -this is not correct
Date:           3/4/96
Day:            Monday
Time:           8:00 AM - 12 noon
Duration:       4 hours
Reason:         Replace bearings
Effect:         Loss of Exhaust-laboratory air.

Critical Shutdown
Building:       NW10
System:         Perimeter heating + boilers + pumps.
Date:           3\5\96
Day:            Tuesday
Time:           7:30 AM - 10:30 AM
Duration:       3 hours
Reason:         To repair or replace leaking 3-way control valve on
                boiler modulating valve.
Effect:         Loss of heat to corridors only. Student rooms/suites
                not affected.

Building:       Campus
System:         FCS-2
Date:           3/5/96
Day:            Tuesday
Time:           10:00 AM - 12 noon
Duration:       2 hours
Reason:         Backup of data
Effect:         Loss of monitoring alarms.

Building:       Campus
System:         FCS-3
Date:           3/4/96
Day:            Monday
Time:           10:00 AM- 12 noon
Duration:       2 hours
Reason:         Backup of data
Effect:         Loss of monitoring alarms.