routine
building - 24
system - electric power
date - 09-23-95
day - saturday
time - 8am until 11am
reason - to tie in new feeder
effect - access controls, bldg power, elevators,
computers, telephones, lighting, chilled water
(cooling), supply ventilation
(cooling/heating), exhaust (lab/general/toilet)
compressed control, compressed lab air, lab
vacuum, condensate return. A.T.T. switch room will be o
n,
on, emergency power will be on.