POWER SHUTDOWN
daemon@ATHENA.MIT.EDU (CVENEZIA%MITPPL.bitnet@mitvma.mit.)
Fri Aug 4 10:57:33 1995
Date: Fri, 4 Aug 1995 10:52 EDT
From: CVENEZIA%MITPPL.bitnet@mitvma.mit.edu
To: CAPPUCCI@MIT.EDU, DCARLSON@MIT.EDU, SHUTDOWNS@MIT.EDU, OPSNOTE@MIT.EDU,
SDVERIFY@MIT.EDU
X-Envelope-To: CAPPUCCI@MIT.EDU, DCARLSON@MIT.EDU, OPSNOTE@MIT.EDU,
SDVERIFY@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Vms-To:
IN%"CAPPUCCI@MIT.EDU",IN%"DCARLSON@MIT.EDU",IN%"SHUTDOWNS@MIT.EDU",IN%"OPSNOTE@
MIT.EDU",IN%"SDVERIFY@MIT.EDU"
ROUTINE
*I HAD RECENTLY SEND YOU EMAIL ON A POWER SHUTDOWN THAT WILL TAKE PLACE
ON 2 CONSECUTIVE SATURDAYS. THE ELEC. SHOP FOUND THAT THIS SHUTDOWN
WILL NEED TO BE DONE 3 CONSECUTIVE SATURDAYS (08-12, 08-19 AND 08-26).
THE INFO AND AREA'S AFFECTED ARE AS FOLLOWS.
BUILDINGS: 1, 3, 8 AND 5
SYSTEMS: ELEC. POWER AND LIGHTING
DATE: 08-12-95, 08-19-95 AND 08-26-95
DAY: SATURDAYS
TIME: 7AM UNTIL 11PM
DURATION: 16 HOURS
REASON: CONSTRUCTION
EFFECT: ALL POWER IN BLDG. 1, ALL POWER IN BLDG. 3, BLDG. 8
(480V) LAB POWER AND BLDG. 5-234.
POWER ONLY AND BUILDING 5-234 (CLASSROOM). ALL POWER
INCLUDES ELEVATORS, LIGHTING, COMPUTERS, CHILLED WATER
(AC COOLING), SUPPLY VENTILATION, SUPPLY COOLING, LAB
EXHAUST, GENERAL EXHAUST AND TOILET ROOM EXHAUST.