[28926] in Hotline Meeting
FCS shutdowns
daemon@ATHENA.MIT.EDU (Jason M. Roush)
Tue Jun 27 16:12:55 1995
Date: Tue, 27 Jun 1995 16:08 EDT
From: "Jason M. Roush" <OPCTEMP%MITPPL.bitnet@mitvma.mit.edu>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, shutdowns@MIT.EDU, opsnote@MIT.EDU
Cc: sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, opsnote@mit.edu,
sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"dcarlson@mit.edu",IN%"cappucci@mit.edu",IN%"shutdowns@mit.edu",IN%"opsnote@
mit.edu"
Following are two shutdown notifications:
Routine
Location: All campus
System: FCS2
Date: 6/29/95
Day: Thursday
Time: 10:00 a.m. - 12:00 noon
Duration: 2 hours
Reason: Backup of data
Effect: Operation center will not be monitoring
alarms during these hours
Routine
Location: All campus
System: FCS3
Date: 6/30/95
Day: Friday
Time: 10:00 a.m. - 12:00 noon
Duration: 2 hours
Reason: Backup of data
Effect: Operation center will not be monitoring
alarms during these hours