[28212] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Shutdown bldg. 13

daemon@ATHENA.MIT.EDU (OPCTEMP%MITPPL.bitnet@mitvma.mit.e)
Mon May 8 13:12:01 1995

Date: Mon, 8 May 1995 13:09 EDT
From: OPCTEMP%MITPPL.bitnet@mitvma.mit.edu
To: SHUTDOWNS@MIT.EDU
Cc: SDVERIFY@MIT.EDU
X-Envelope-To: SDVERIFY@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Vms-To: IN%"SHUTDOWNS@MIT.EDU"

Following are two shutdown notifications:

Routine

        Building:               13, select core rooms
        System:                 Air Handler 1, Air Handler 2
        Date:                   5/10/95
        Day:                    Wednesday
        Time:                   5:00 p.m. - ?
        Duration:               Until air supply is needed
        Reason:                 Chilled water coil repairs
        Effect:                 No air supply ventilation, cooling or
                                heating until air supply is needed