SHUTDOWN BLDG 48
daemon@ATHENA.MIT.EDU (OPCTEMP%MITPPL.BITNET@mitvma.mit.e)
Mon Apr 3 14:18:06 1995
Date: Mon, 3 Apr 1995 14:16 EDT
From: OPCTEMP%MITPPL.BITNET@mitvma.mit.edu
To: DCARLSON@MIT.EDU, CAPPUCCI@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Envelope-To: CAPPUCCI@MIT.EDU, DCARLSON@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Vms-To: IN%"DCARLSON@MIT.EDU",IN%"CAPPUCCI@MIT.EDU",IN%"SHUTDOWNS@MIT.EDU"
THE FOLLOWING IS A CRITICAL SHUTDOWN
CRITICAL
BLDG: 48
SYSTEM: AIR HANDLER 4
DATE: 4/3/95
DAY: MONDAY
TIME: 7:00 PM - 11:00 PM
DURATION: 4 HOURS
REASON: REINSTALLATION OF CHILLED WATER COIL
EFFECT: NO VENTILATION FROM AIR HANDLER 4 IN BLDG 48