B2 shutdown 4-16

daemon@ATHENA.MIT.EDU (John Chase)
Mon Mar 27 12:58:30 1995

To: dcns-cluster@MIT.EDU
Cc: hotline@MIT.EDU
Date: Mon, 27 Mar 1995 12:58:14 EST
From: John Chase <jchase@MIT.EDU>


 
        BLGD:           2
        SYSTEM:         ALL ELECTRIC POWER AND LIGHTING, EMERGENCY
                        POWER WILL BE ON
        DATE:           4/16/95
        DAY:            SUNDAY
        TIME:           12:00 AM - 6:00 AM
        DURATION:       SIX (6) HOURS
        REASON:         REPLACE 2400 VOLT FUSE HOLDERS ON MAIN SWITCH
                        FOR BLGD 2
        EFFECT:         NO POWER FOR SIX HOURS


  How do we want to handle this? Anyone want some OT?
  
  John
  
  Option 1.
	Shut it down friday night and open monday morning.
	
  Option 2. 
        Someone come in Saturday Night, then someone come in
	sunday am. 
	
  Option 3.
	Shutdown friday night and someone come in sunday am. 
 